Buying guide · 04 — Plan the installation

How to Integrate CNC Glass Drilling into an Existing Line

Four interfaces to plan before inserting a CNC glass drilling station into an existing line: conveying direction, table height, upstream and downstream processes, and control interfaces. Based on BLM's A98 line case.

A98 drilling equipment installed in a customer architectural glass production line
Customer photo: A98 drilling equipment in a line. Published case text describes the process sequence but gives no cycle-time or accuracy figures.
The short answer

Treat the drilling machine as one station in a material-flow system. Four interfaces have to be agreed before it is ordered: the direction the panel travels, the working height at the hand-off, the equipment immediately before and after, and how programmes and production data reach the controller. The BLM A98 line case shows the process side of that equation; the remaining three are plant-specific and can only be settled against your own layout and systems.

Start from the panel route, not the machine

Adding a drilling station to an existing line rarely fails because the machine cannot drill the holes. It fails because the panel arrives in the wrong orientation, at the wrong height, or at a rate the downstream washer cannot absorb. A new machine that produces good parts but creates a manual transfer at each end has simply moved the bottleneck.

Draw the current route first — loading, edging, washing, tempering or whatever follows — and mark every place where a person currently lifts or turns a panel. The integration job is to remove those moves without creating a new queue.

The A98 case: what a connected drilling station looks like

BLM's published A98 line integration case describes an architectural glass line where the drilling equipment was connected to bilateral machines, upper and lower tables and cleaning machines for large glass panels. The stated aim was continuous production of large architectural glass drilling work. That gives us a process sequence, not a performance claim:

01Loading / unloading table
→
02Bilateral edging
→
03A98 CNC drilling & milling
→
04Washing & drying
→
05Unloading / sorting

The case text contains no cycle time, positioning accuracy, yield, panel dimensions or before/after comparison. BLM does not publish figures that have not been recorded, so this guide describes the interfaces and the information needed to plan them, and leaves the performance fields empty. The A98 case page lists what a buyer should prepare before discussing a similar line.

Source note. The A98 line-integration case connects the drilling station with bilateral edging machines, upper and lower loading tables and cleaning machines for inline processing of large architectural panels.

Interface 1 — Conveying direction and transfer geometry

Decide which way the glass enters and leaves the drilling station, and whether the panel must turn, flip or be re-referenced between stations. This sounds trivial until the machine arrives: a left-to-right drilling centre inserted into a right-to-left line needs either a transfer unit or a change in the whole production route.

BLM's supplied documents describe roller conveying and automatic infeed/outfeed on several shower glass lines, but they do not specify conveying direction, transfer orientation or interface elevations for the A98 case. Those are project-specific and cannot be taken from a catalogue. On the plan view you send us, mark:

Conveying details to confirm on your plan

  • Glass travel direction through the drilling station
  • Whether the panel stays in one orientation or is turned or flipped
  • Where the operator loads, and where finished panels are staged
  • Transfer points and the equipment immediately upstream and downstream
  • Aisle width, service access and any height restriction

Interface 2 — Working height at the hand-off

Table height is the quietest integration failure. If the drilling table, the edger outlet and the washer inlet are not at a compatible elevation, the transfer either needs a lift or a ramp — and both add handling risk for large, heavy glass.

Several BLM product drafts, including the A98 detail, list a table height of 900 ± 20 mm. That is the machine's nominal working height, not a promise that it matches your line. Confirm the actual conveyor and inlet heights of your existing equipment, and check them against the machine drawing before the foundation or supports are built. If the drilling station is being linked to a vertical line instead, see Vertical vs. Horizontal Glass Drilling Machines — the orientation changes the entire hand-off geometry.

Interface 3 — Upstream and downstream processes

In the A98 case, drilling sits between bilateral edging and washing, with upper and lower tables handling the panels at each end. That is a typical architectural glass sequence, and it is the reason the architectural glass solution treats drilling as a station rather than a product purchase.

Three questions settle this interface:

For shower door work the sequence is usually shorter — drilling, optional milling or polishing, then washing — and the shower door glass processing line shows how a single machine grows into a linked line as volume increases.

Interface 4 — Control and data interfaces

The machine has to receive the right programme for the right panel. BLM drafts describe an industrial PC interface, online drawing import, DXF/CAD files, barcode or QR scanning that reads glass information and assigns the hole pattern automatically, and ERP connection. Old-site articles also discuss CAD/DXF import and ERP-integrated drilling. These are described as available functions, not as a defined interface specification.

What has not been supplied is the protocol level detail: the PLC or controller handshake, the signal list for ready / busy / fault, the data format for job and hole-pattern records, and whether your MES or ERP expects a push or a pull. That is why the integration enquiry asks about your existing control system. Do not assume that "ERP connection" on a feature list means your specific system can talk to the machine on day one; agree the interface specification in writing before the order.

Information to send before an integration proposal

  • A dimensioned plant layout with the proposed drilling position
  • Existing equipment list, with inlet and outlet heights
  • Glass size and thickness range, minimum and maximum
  • One representative hole drawing or DXF file
  • Target output and the current bottleneck
  • ERP / MES system in use, and who owns the interface on your side

A practical project sequence

1. Site survey and measurement — panel route, heights, access, services. 2. Layout confirmation — machine position, infeed/outfeed, transfer and orientation, signed off before manufacture. 3. Interface definition — mechanical hand-off drawings and the control/data specification, both in writing. 4. Installation and commissioning — levelling, alignment, programme import and trial panels from your own drawings. 5. Training and acceptance — operator training, maintenance hand-over, and an agreed acceptance test using real parts.

No durations, response times or on-site service windows are quoted here: BLM's existing documents contain conflicting after-sales commitments, and a single confirmed scope has to be agreed per project before any of them are published.

Planning to add drilling to an existing line?

Send your plant layout, the equipment before and after the drilling station, and your current glass specifications. Our engineers will review the mechanical and control interfaces before proposing a configuration.

Request a Project QuoteWhatsApp instead

FAQ

What information does BLM need before quoting a line integration?

A dimensioned layout, the equipment upstream and downstream with their working heights, glass size and thickness range, one representative hole drawing, target output, and the ERP/MES system in use. The A98 case page has a short pre-installation checklist, and the project enquiry form accepts a layout description plus optional drawings.

Can the drilling machine connect to our existing edging and washing machines?

Mechanically, the A98 case shows drilling linked to bilateral machines, upper and lower tables and cleaning machines. Whether your specific equipment can be linked depends on conveying direction, table height and transfer geometry — all project-level checks, not catalog features.

Does BLM publish cycle time or accuracy for the A98 line case?

No. The published case text contains no throughput, accuracy, yield or before/after data, so none is shown here. Recorded process data has to be supplied and confirmed before any performance figure is published.

Can the machine import our DXF drawings and talk to our ERP?

BLM drafts describe DXF/CAD import, barcode-driven hole-pattern assignment and ERP connection as available functions. The protocol, signal handshake and data format must be defined against your system in the project specification. State your ERP/MES platform in the enquiry so the interface can be scoped.


Draft figures marked “Pending spec confirmation” come from BLM product documents and are replaced by a signed specification sheet before publication. BLM does not publish unrecorded performance or pricing data.